CTH N - CTH CE to CTH KK

Updated August 8, 2024

County N is currently closed to traffic for Phase 2 water main replacement and scheduled to re-open in late August.

N - CTH KK to CTH CE - Town of Buchanan

Project Description

This project is for design, right-of-way, and ultimate reconstruction of this segment of County N. A 3-lane urbanized pavement section is planned as well as expanding the existing Emons/Buchanan Rd roundabout in order to improve capacity. Federal funding has been awarded through the STP-Urban program.

Project Status

Right-of-way acquisition and utility coordination are currently ongoing. Utility relocations are currently scheduled throughout 2024and 2025with roadway reconstruction rescheduled for 2026.

Traffic Impacts

County N closed to traffic in late July to allow for Phase 2 of watermain reconstruction. Local and emergency access is being maintained. A signed detour is in place and utilizes County KK, WIS 441, and County CE. County N is currently scheduled to reopen to traffic in late August.

Design Engineer

Westwood Infrastructure

Project Schedule

  • Design - 2022 and ongoing
  • Right-of-Way Acquisition – 2023 and ongoing
  • Utility Relocation – 2024 and 2025
  • Roadway reconstruction - 2026

Preliminary Construction Plans

PIM # 3 Public Involvement Meeting Information (August 2023)

PIM #2 Public Involvement Meeting Information (February 2022)

PIM #1 Public Involvement Meeting Information (July 2018)