CTH N - CTH CE to CTH KK
Updated August 8, 2024
County N is currently closed to traffic for Phase 2 water main replacement and scheduled to re-open in late August.
N - CTH KK to CTH CE - Town of Buchanan
Project Description
This project is for design, right-of-way, and ultimate reconstruction of this segment of County N. A 3-lane urbanized pavement section is planned as well as expanding the existing Emons/Buchanan Rd roundabout in order to improve capacity. Federal funding has been awarded through the STP-Urban program.
Project Status
Right-of-way acquisition and utility coordination are currently ongoing. Utility relocations are currently scheduled throughout 2024and 2025with roadway reconstruction rescheduled for 2026.
Traffic Impacts
County N closed to traffic in late July to allow for Phase 2 of watermain reconstruction. Local and emergency access is being maintained. A signed detour is in place and utilizes County KK, WIS 441, and County CE. County N is currently scheduled to reopen to traffic in late August.
Design Engineer
Westwood Infrastructure
Project Schedule
- Design - 2022 and ongoing
- Right-of-Way Acquisition – 2023 and ongoing
- Utility Relocation – 2024 and 2025
- Roadway reconstruction - 2026
Preliminary Construction Plans
PIM # 3 Public Involvement Meeting Information (August 2023)
PIM #2 Public Involvement Meeting Information (February 2022)
PIM #1 Public Involvement Meeting Information (July 2018)