Highway Project Updates

2024 County Highway Construction and Paving Project Updates as of 11/07/2024

CTH A

A - CTH JJ East to CTH JJ West - Town of Grand Chute

Project Description

This project will improve the existing asphaltic surface by placing an asphalt leveling layer and asphalt overlay for this segment of highway. The paved shoulder will also be widened to current County standards. Culverts and other roadway appurtenances may also be improved, replaced, or upgraded to current standards.

Project Status

Milling and paving of the asphalt pavement was completed in mid-October. Crews are scheduled to complete shouldering, guardrail replacement, and final finishing operations in early November.

Traffic Impacts

County A remains open to traffic. Remaining work will be completed utilizing flagging operations and/or shoulder closures. 

CTH CB

CB - WIS 15 to CTH JJ - Village of Greenville and Town of Grand Chute

Project Description

Outagamie County conducted an engineering study to evaluate potential alignments for the extension of County CB from WIS 15 to County JJ. The planning, design, construction and maintenance of roadways within the community is a critical component of safe and efficient travel, smart growth planning, and economic development.

Project Status

Recommended alignment was presented to the public in June 2021. Presentations were made to local officials in September 2021. Mapping of the proposed corridor is under consideration by each municipality.

Traffic Impacts

Pending

Design Engineer

Oneida Engineering Services

More Information

CTH D

D - WIS 76 to CTH XX - Town of Deer Creek

Project Description

This project includes a drainage study to determine improvements to the area, design, and ultimate construction of roadway, drainage, and pavement improvements. Culverts and other roadway appurtenances will also be improved, replaced, or upgraded to current standards.

Project Status

County crews completed roadway and drainage construction in fall 2023 from the south project limit (WIS 76 intersection) to the Oak Road intersection. This segment was reclaimed and paved in May 2024.

Crews completed pavement replacement of the northern portion of the project (Oak Road to CTH XX) in October. Drainage improvements have also been completed. Final finishing and shouldering is currently underway. The surface layer of asphalt pavement is currently scheduled to be placed in 2025 over the entire project.

Traffic Impacts

County D is currently closed to thru traffic with local access maintained. A signed detour has been posted and utilizes WIS 76, USH 45, and Waupaca County D / Outagamie County XX.

Design Engineer

Westwood Infrastructure

More Information

CTH F

F - Birch Road to CTH M - Towns of Deer Creek, Maine

Project Description

This project will improve the existing asphaltic surface by reclaiming, regrading, and installing a new asphalt pavement for this segment of highway. Culverts and other roadway appurtenances will also be improved, replaced, or upgraded to current standards.

Project Status

Culvert replacement began in early May and asphalt paving was completed in late May. Placement of the surface layer of asphalt is scheduled for 2025.

Traffic Impacts

Roadway is open to traffic, 2024 work is complete. The surface layer of asphalt is scheduled for 2025.

Design Engineer

Outagamie County 

CTH G

G - Isaar Road to CTH Y - Town of Seymour

Project Description

This project is for the design, right-of-way, and future reconstruction of this segment of highway. Associated improvements will include lowering the roadway profile to allow for a wider paved surface and shoulders. Culverts and other roadway appurtenances will also be improved, replaced, or upgraded to current standards.

Project Status

Final design is currently underway. Right-of-way acquisition is currently underway. Construction is scheduled for 2025. A public information meeting was held in late April with materials available on the project website.

Traffic Impacts

County G will be closed to through traffic during construction with local access maintained. A signed detour will be posted and is likely to utilize WIS 55, County VV, and County Y.

Design Engineer

Outagamie County

More Information

CTH JJ

JJ - CTH A to WIS 47 - Town of Grand Chute

Project Description

This project is for the design, right-of-way and future reconstruction of County JJ to an urban cross section. Current and planned development in the area has prompted the need for reconstruction to improve safety & operational efficiency, improve drainage, and provide multimodal accommodation. This project also includes utility improvements for the Town of Grand Chute and replacement of the existing railroad crossing located east of Wren Drive.

Project Status

Preliminary design continues. Updated project costs and schedules are being prepared for budgeting and planning purposes.

Traffic Impacts

Pending

Design Engineer

Westwood Infrastructure

More Information

JJ - (OLD STH 15) Givens Road to Greendale Road - Village of Hortonville

Project Description

This project will reconstruct portions of the roadway and replace the existing pavement through the Village of Hortonville upon completion of a jurisdictional transfer of former WIS 15.

Project Status

An all-way stop condition was put into effect at the intersections of County JJ (Old WIS 15) & Mill Street and County JJ & Nash Street in late 2023. Preliminary designs were presented to the public in early March and downtown business owners in May in order to confirm the typical cross section. Construction is currently scheduled to begin in 2026.

Traffic Impacts

Pending

Design Engineer

McMahon

More Information

JJ - (OLD STH 15) B-44-709 over Black Otter Creek Village of Hortonville

Project Description

This project is for the design, right-of-way, and future replacement of the bridge structure to current standards upon completion of a jurisdictional transfer of former WIS 15.

Project Status

Preliminary design and hydraulics analysis is complete, including determination of initial right-of-way impacts. Development of the right-of-way plat is underway which will be followed by acquisition. Construction is currently scheduled for 2026.

Traffic Impacts

Pending

Design Engineer

JT Engineering

CTH KK

KK - B-44-003 Bridge over Kankopot Creek Town of Buchanan

Project Description

This project is for the design, right-of-way, and replacement of existing bridge B-44-003 over Kankopot Creek. In addition, approach pavements, culverts, and other roadway appurtenances may also be improved, replaced, or upgraded to current standards.

Project Status

Reconstruction of the bridge was completed in late October under a let contract. County crews are currently completing approach reconstruction and placement of the asphalt pavement with guardrail placement and final finishing items to follow.The project is currently anticipated to be complete in mid November.

Traffic Impacts

County KK is currently closed to thru traffic with local access maintained.A signed detour has been posted and utilizes WIS 55, County CE, and County GG.

Design Engineer

Westbrook Associated Engineers

More Information

CTH N

N - CTH KK to CTH CE - Town of Buchanan

Project Description

This project is for design, right-of-way, and ultimate reconstruction of this segment of County N. A 3-lane urbanized pavement section is planned as well as expanding the existing Emons/Buchanan Rd roundabout in order to improve capacity and safety. Federal funding has been awarded through the STP-Urban program.

Project Status

Right-of-way acquisition and utility coordination are currently ongoing. Utility relocations are currently scheduled to occur throughout 2024 and 2025. Roadway reconstruction has been rescheduled to occur in 2026 (previously 2025). Impacted property owners should expect to receive correspondence in late October that provides an update on the status of right-of-way acquisition and next steps.

Traffic Impacts

During future roadway reconstruction, County N will be closed to thru traffic during construction with local access maintained. A signed detour will be posted and is anticipated to utilize County KK, WIS 55, and County CE. There may be additional traffic impacts related to utility relocation prior to the roadway reconstruction in 2026.

Design Engineer

Westwood Infrastructure

More Information

CTH OO

OO - Richmond Street (STH 47) to 750-ft E. of Meade Street - City of Appleton, Town of Grand Chute

Project Description

This project will improve the existing concrete pavement by making spot joint repairs and concrete panel replacements for this segment of highway. Culverts and other roadway appurtenances may also be improved, replaced, or upgraded to current standards.

Project Status

A portion of the project has been awarded for construction. Construction is currently underway between Ballard Road and Meade Street with a few additional spot repairs located between Ballard Road and Conkey Street.

Traffic Impacts

County OO is currently closed to traffic between Meade Street and Park Drive Lane.
A signed detour is posted and utilizes County E (Ballard Road), I-41, and WIS 47 (Richmond Street). Local access is being maintained between Park Drive Lane and Ballard Road. Thru traffic along County OO is suggested to follow the detour in order to avoid travel delays.

Design Engineer

CBS Squared 

CTH PP

PP - WIS 54 to WIS 54 - Towns of Center, Black Creek

Project Description

This project will improve the existing asphaltic surface by placing an asphalt leveling layer and asphalt overlay for this segment of highway. The paved shoulder will also be widened to current County standards. Culverts and other roadway appurtenances may also be improved, replaced, or upgraded to current standards.

Project Status

Asphalt resurfacing and major work items have been completed.Final finishing and sign replacements are anticipated to be completed in early November and will complete the project. A portion of the project is currently being utilized as part of a planned detour of WIS 47 under a WisDOT project.

Traffic Impacts

County PP remains open to traffic. Remaining work will be completed utilizing flagging operations and/or shoulder closures. 

CTH U

U - County S to County EE - Town of Oneida, Brown County

Project Description

This project is for the design, right-of-way, and future rehabilitation of this segment of County U. The associated improvements are anticipated to include pavement replacement, spot regrading, drainage and safety improvements, widening the shoulder to current standards, and improving, replacing, or upgrading roadway appurtenances to current standards.

Project Status

Preliminary design is complete. A Public Involvement Meeting was held in late May with materials available on the project website. Development of the right-of-way plat is underway. Right-of-way acquisition and final design will follow. Construction is currently scheduled to begin in 2026 and may be completed over multiple seasons.

Traffic Impacts

During construction, the project area will be closed to through traffic. A signed detour will be posted, and is likely to utilize County S, County J, County E, and County EE.

More Information

CTH VV

VV - Isaar Rd to CTH Y - Town of Seymour

Project Description

This project will lower the roadway profile to allow for a wider paved surface and shoulders. The roadway will be pulverized, regraded, and a new asphaltic pavement will be placed. Other spot improvements are also anticipated.

Project Status

Roadway reconstruction, placement of the lower lift of asphalt pavement, and final restoration was completed in 2023. Crews are currently investigating and addressing areas of unstable base material throughout the project.

Traffic Impacts

County VV is currently open to traffic.

Design Engineer

Outagamie County 

CTH Z

Z - County ZZ to Outagamie Rd - Town of Buchanan

Project Description

This project is for design, right-of-way, and ultimate reconstruction of County Z to current County highway standards. Federal funding has been awarded through the STP-Rural program for the eastern portion with the western portion being locally funded. Both segments will be combined into a single project for construction.

Project Status

Final design and right-of-way acquisition are complete.Utility relocation and adjustment is currently scheduled to begin in fall 2024 and continue until roadway reconstruction in 2025.Roadway reconstruction will occur throughout the 2025 season.

Traffic Impacts

County Z will be closed to thru traffic during construction with local access maintained. A signed detour will be posted and is anticipated to utilize WIS 55, County CE, and Brown County D.

Design Engineer

raSmith

More Information

Future Highway Projects 

Wisconsin Department of Transportation Projects

For information on state and US highway projects in Outagamie County, contact the Wisconsin Department of Transportation or visit their website pages linked here: